A community choices process has been launched to consult and engage with communities on park improvements at various parks within West Lothian that are identified for improvements as part of the councils capital investment programme.

This is a two staged community consultation process, the first stage will be undertaken during November 2020 and involves communities completing a survey to provide information on their local park, this information will then be used to prepare a report on the park with a plan of improvement during the start of 2021. The second stage of the community choices process will involve the communities in agreeing the plan for the park and this will be undertaken during March 2021. Following agreement on the park improvement plans the agreed improvements to be undertaken for completion by March 2022.

If you have any queries regarding the above parks and the community choices process for park improvements please contact Becky Plunkett via email (becky.plunkett@westlothian.gov.uk).

Reviewing projects

-

A community choices process has been launched to consult and engage with communities on park improvements at various parks within West Lothian that are identified for improvements as part of the councils capital investment programme.

This is a two staged community consultation process, the first stage will be undertaken during November 2020 and involves communities completing a survey to provide information on their local park, this information will then be used to prepare a report on the park with a plan of improvement during the start of 2021. The second stage of the community choices process will involve the communities in agreeing the plan for the park and this will be undertaken during March 2021. Following agreement on the park improvement plans the agreed improvements to be undertaken for completion by March 2022.

If you have any queries regarding the above parks and the community choices process for park improvements please contact Becky Plunkett via email (becky.plunkett@westlothian.gov.uk).

Voting projects

-

A community choices process has been launched to consult and engage with communities on park improvements at various parks within West Lothian that are identified for improvements as part of the councils capital investment programme. The parks are:

  •  King George V Playing Fields, Uphall
  •  Bellsquarry Recreation Ground, Bellsquarry, Livingston
  •  Craigton Park, Winchburgh
  •  Langton Park, East Calder
  •  Letham Park, Pumpherston

This is a two staged community consultation process, the first stage was undertaken during November 2020 and involved communities completing a survey to provide information on their local park, this information was then used to prepare a report on the park with a plan of improvement during the start of 2021.

The second stage of the community choices process involves the communities in agreeing the plan for the park and this will be undertaken during March - April 2021, more information can be found at West Lothian Community Choices. Following agreement on the park improvement plans the agreed improvements to be undertaken for completion by March 2022.

If you have any queries regarding the above parks and the community choices process for park improvements please contact Becky Plunkett via email (becky.plunkett@westlothian.gov.uk).

Reviewing voting

-

A community choices process has been launched to consult and engage with communities on park improvements at various parks within West Lothian that are identified for improvements as part of the councils capital investment programme. The parks are:

  •  King George V Playing Fields, Uphall
  •  Bellsquarry Recreation Ground, Bellsquarry, Livingston
  •  Craigton Park, Winchburgh
  •  Langton Park, East Calder
  •  Letham Park, Pumpherston

This is a two staged community consultation process, the first stage was undertaken during November 2020 and involved communities completing a survey to provide information on their local park, this information was then used to prepare a report on the park with a plan of improvement during the start of 2021.

The second stage of the community choices process involves the communities in agreeing the plan for the park and this will be undertaken during March - April 2021, more information can be found at West Lothian Community Choices. Following agreement on the park improvement plans the agreed improvements to be undertaken for completion by March 2022.

If you have any queries regarding the above parks and the community choices process for park improvements please contact Becky Plunkett via email (becky.plunkett@westlothian.gov.uk).

Finished budget

-

A community choices process was launched to consult and engage with communities on park improvements at various parks within West Lothian that are identified for improvements as part of the councils capital investment programme. The parks are:

King George V Playing Fields, Uphall Bellsquarry Recreation Ground, Bellsquarry, Livingston Craigton Park, Winchburgh Langton Park, East Calder Letham Park, Pumpherston

The two process has been undertaken in stages. Stage one involved a community survey which was undertaken during November 2020 and involved communities, this information was then used to prepare a report on the park with a plan of improvement during the start of 2021.

Stage two of the community choices process involved the communities voting on the priorities of the park improvements and was undertaken during March - May 2021. The top five priorities for each park is listed below, please note this is not the full list of the park improvements that will be undertaken but shows the similarities and differences between the top priority improvements to be undertaken in each park.

The next stage will be to prepare tender documentation and to tender for the planned works with the improvements to be undertaken for completion by March 2022.

Thank you to everyone who was involved in the process, more information can be found at West Lothian Community Choices

If you have any queries regarding the park improvements please contact Becky Plunkett via email (becky.plunkett@westlothian.gov.uk).

If you have any queries on the Community Choices process or CONSUL itself, please contact us via email (WestLothianCommunityChoices@westlothian.gov.uk)

Bellsquarry Park, Livingston

  • Bellsquarry Park, Livingston £30,000

Craigton Park, Winchburgh

  • Craigton Park, Winchburgh £40,000

KGV Playing Field, Uphall

  • KGV Playing Field, Uphall £45,000

Langton Park, East Calder

  • Langton Park, East Calder £26,000

Letham Park, Pumpherston

  • Letham Park, Pumpherston £26,000

Budget investments' proposals located geographically